Upcoming Closure on Pioneer Street

7 PM Friday, November 1 - 11 PM Monday, November 11

Pioneer Street will be CLOSED between Discovery Drive and 56th Place from 7 PM Friday, November 1 to 11 PM Monday, November 11. During this period, city contractors will complete installation of a major stream culvert and associated utility work. 

The detour route along S Royle Road, Wells Drive, Timm Road, S 6th Way, and S 56th Place from previous closures will be in effect. Discovery and Pioneer Canyon Drive will remain open for local business access. Detour map (PDF)

Additional project details below detour map.

Detour map for upcoming Pioneer Street closure.

Pioneer Widening and Discovery Drive Roundabout Project Update, October 31, 2024

Last weekend, we closed Pioneer Street between 56th Place and Discovery Drive for a significant culvert installation as part of the Pioneer Widening project. Although progress was made, the contractor was unable to complete the culvert work due to heavy rainfall on Saturday.

This culvert work operates under a regulated schedule, which has now been extended through November 11. The job itself is complex, requiring multiple days without traffic in the area to handle the size and intricacies of the culvert, alongside crucial adjacent utility work. To address these needs, the City has approved extending the upcoming closure of Pioneer Street between 56th Place and Discovery Drive, scheduled now from 7 PM Friday, November 1, through 11 PM Monday, November 11.

This decision was not made lightly; it followed careful coordination between the City and the contractor to ensure that the closure would proceed as smoothly as possible, with commitments to the following:

  • The contractor has added extra pumps and will be closely monitoring weather to prevent further disruptions from rainfall during this work period. They are also completing additional prep work and material staging ahead of the closure to maximize efficiency and ensure the work will be completed within the timeframe.
  • To ease traffic flow during the closure, 53rd Place will be open for northbound traffic during the PM rush hour (3 PM–7 PM) on weekdays. Drivers can take 53rd Place to Pioneer Canyon Drive, then head west to reconnect with Pioneer.
  • Access to businesses on 53rd Place (Mountain View Dental and Ridgefield Physical Therapy) will remain available from Pioneer Canyon during business hours, though south bound 53rd Place will be closed beyond these business entrances.
  • Once this closure concludes, the temporary signal at 53rd Place will be removed, and the intersection will convert to right-in/right-out access, per the original plan. Candlestick style traffic barricades will be installed along the center line to emphasize that no left turn is permitted. 
  • The contractor and City will closely monitor the closure area at key intersections and add extra flaggers to detour routes if needed to keep traffic moving smoothly.

We recognize the significant impact these past two months of construction have had on travel through the area. Once this closure is complete, we’ll all see a break from the shifting traffic patterns as the contractor wraps up culvert installations and focuses on widening the south side of Pioneer, giving everyone some breathing room before heavy work picks up again in 2025. Thank you for your continued patience and flexibility as we work together to keep Ridgefield moving forward.

Other Traffic Alerts

N Royle Road - October 31: Single lane closure in effect on N Royle Road at Paradise Pointe subdivision from 10 AM - 3 PM on Thursday, October 31 to allow contractors to construct bases for streetlights.

S 21st Place, S 4th Way, S 25th Place - October 22 - November 1: A single lane closure will be in effect on Tuesday, October 22 through Friday, November 1 from 8 AM - 6 PM to allow contractors to complete prep work for curbs on both sides of the street.

Hillhurst Road - October 21 - November 8: A lane shift will be in effect Mondays, Tuesdays, Thursdays and Fridays 9 AM - 5 PM and 10 AM - 5 PM on Wednesdays from October 21 through November 8 to allow contractors to complete work in the shoulder.

View the online Traffic Map

Thank you for your patience and support.

Our first priority is safety! So, please use additional caution anywhere work is underway, be considerate of flaggers and workers, and report any safety concerns by calling us at 360-887-3557.